PERSON
8X6 DESIGN STUDIO
- OMARA
- Their tile is estimated to be arriving today. I will call once the day starts to confirm the time and give you a confirmation once it’s on site.
- Their Vinyl flooring freight isn’t scheduled yet but once it’s scheduled for delivery i will give the date it’s arriving.
- They’re ready for paint once we have an availability.
- Punch/list elements were discussed and approved by the homeowner during a zoom call that occurred back on April 16th.
- Other notes : I’m not sure if Milan has an update for us in regards to their bar. The last thing that happened was that zoom call that we had. He mentioned that he would be getting back to us but I’m not sure if he already did with you and he’s all good or if he other further questions and details to be discussed.
- GODA
- His tile is on site in his garage already. Let me know when you’d like me to meet installer on site for assistance if needed.
- His Vinyl is expected to arrive next Monday or Tuesday.
- Blaze is on board and I believe is starting soon after paint.
- Plumbing fixtures are in his garage.
- Me and Him are meeting next week to submit an order on his punch list elements; such as cabinet handles and bath accessories. I will send you the door handle styles so you could order them.
- Sebastian’s microwave opening at the bar isn’t to specs. I believe he’s going to cut it to be perfect at the end when he returns but I think Chandra already has his appliances people installing this so I'm not sure if it’d delay things later on if we have to wait for Sebastian to adjust the opening for the microwave according to specs or delay painters to come back for touchups.
- GONA
- As mentioned before; the things that are outstanding on my end were the following and they’re already in place!
- Their backsplash tile is ordered; I will follow up with Tilebar to see if they shipped.
- their cabinet handles and accessories are being picked up today and will be dropped off to the site. A confirmation will be sent to you guys once it’s there.
- I will talk to Jayson as an alternative .. I’m going to be scheduling the meeting; please let me know if you can be there as i may need your assistance if he requests anything for trim to be tweaked.
- Wallpaper still isn’t ordered and this will be an issue if we don’t submit it soon because they have a long lead time : Brooke .. Please let me know if you have an update on this.
- Exterior door : i confirmed the style with Jose and Gona .. It looks like Jose was looking to make sure the sizes that he sent was confirmed. The style of the door i already confirmed the same day he sent the specs but I have no clue what the installers would need in terms of actual size so i can’t confirm that the sizes he sent would work for the installer with no issues. Please let me know if these sizes he sent was good and i can get Sirisha to submit payment directly as mentioned before if it’s easier.
- MUNAFO
- I met with him back on April 15 and he’s all done on my end in terms of materials and finishes .. He approved his flooring, paint, trim, design overall while we were in that meeting on April 15.
- I texted back around the week of April 8th requesting vinyl square footage.
- If you guys have these numbers i can have him submit the orders for him. He can stock everything in his Garage.
- RAVI PATEL
- He called me yesterday and send me his construction estimate from Miguel. I know Dan Johnston was having a meeting with him back on Tuesday. Ravi wants us to get him a break down for him to see what would make sense on his end from the proposal they provided him. If you’d like me to directly communicate with Miguel that’s fine, i just need to know. Otherwise; please let me know if we could get him that breakdown.
- AL COLANTONI
- I met with him over zoom and discussed his stools and living room furniture that he needed help with and he’s all good. He mentioned that he still has outstanding construction punch-list elements… I’m not sure what they are but please let me know if i can help on it.